Project overview
This project is part of the City’s Integrated Road Program, an initiative that aims to streamline the design and construction of infrastructure projects and improve collaboration during project delivery through the bundling of various road improvement projects. A map illustrating the project area is shown below.
The following are the improvements that will be implemented as part of this project:
- Road rehabilitation
- Cycling facilities
- Road safety
- Stormwater management
- Culvert replacement
- Transit infrastructure
- Noise walls
- Landscaping
The proposed improvements will support a range of transportation modes, including walking, cycling, transit and other vehicles, ensuring the community remains vibrant and active. The proposed improvements will also support the City’s Vision Zero initiative by prioritizing the safety and access of our most vulnerable road users.
-
1Preliminary design phase: October 2020 - February 2022
Complete studies and assessments, carry out public consultation, and elect the preferred design concept.
-
2Detailed design and tender phase: February 2022 – July 2023
Complete field investigations and property acquisitions, secure all required permits and approvals, develop the detailed design, issue tender, review call for submissions, bid submissions, selection process, and award contract to successful bidding contractor.
-
3Construction phase: September 2023 - November 2024
Implement the proposed improvements, including pavement rehabilitation and construction of new cycling facilities, pedestrian crossings, drainage infrastructure, noise walls, transit infrastructure, traffic signals and street lighting upgrades and intersection improvements.